Day T-Plus 135: August 25.

The redwood trim along the windows and doors is almost completely on. From the southeast corner.

Day T-Plus 138: August 28.

The soffit is on around the house. The southeast corner, from the south side.

More soffit on the south side.
And on the southeast corner.
The porch floor is on, and part of the ceiling too.
A little on the inside now... The drywall and prep for painting is complete. This is the southeast corner of the house, in the living room.
Still in the living room, looking south onto the porch.
Out on the porch, looking west into the dining room.
Looking into the dining room, looking south. That extra plywood will be gone sometime...
Looking east onto the porch, from the dining room.
Looking up the stairs. The window is on the west wall.
Looking down the stairs—the small square windows are on the south side.
Conrad's office, looking north. This is the northwest corner of the house.
Looking east into the living room, down the main hallway. The doorway on the right leads into the kitchen.
Day T-Plus 142: September 1.

The redwood siding is finally going up! This is the north side of the house.

The northwest corner of the house (Conrad’s office).
The southwest corner of the house. The tarp is on the second floor to keep rain from getting in until the siding is on up there.
The south side side of the house, with Margaret, Lahoma and Ozma on deck. Siding is going up on the east side as well.
The northeast corner of the house, with the AC unit sitting on the front porch until the final grating is done.

More coming as soon as there is progress!